Arrive on site and off load steel. |
![]() |
Set out main beams and attach Purlin cleats |
![]() |
Assemble goal post of main beam and columns. Attach purlin to stabilise structure and to establish width of bays. |
![]() |
Once all main steel is erected fix remaining purlins to cleats on main beams. |
![]() |
Lay decking boards to first floor level |
![]() |
Straighten columns and fix to floor. Tighten bolts on purlins |
![]() |
Erect staircases and fit handrail |
![]() |
Clean up |